Improvement of energetic effectiveness of ice palace «Pesrtetsy-Arena», Pestretsy, the Republic of Tatarstan

Improvement of energetic effectiveness of ice palace «Pesrtetsy-Arena», Pestretsy, the Republic of Tatarstan

 

Within the framework of improvement of energetic effectiveness of the ice palace «Pesrtetsy-Arena», Pestretsy, the Republic of Tatarstan in 2013 it was decided t construct a cogeneration plant based on engine MAN E2842 E312 (250 kW) equipped with Motortech systems: ignition system based on MIC500, mixture system based on VariFuel2, control system based on AIO-NTC.

In difficult conditions with significant time limits to accelerate the construction of this plant, “MT Group” implemented promptly delivery of engine engine MAN E2842 E312 in 1 (one) month.

Total output of mini-CHP is:
240 kW – electric;
365 kW – thermal.

Previous project Next project 
На нашем сайте используются cookie-файлы, в том числе в части сервисов веб-аналитики. Используя сайт, вы соглашаетесь на обработку персональных данных при помощи cookie-файлов а также соглашаетесь с «Политикой в отношении обработки персональных данных».

Получить консультацию

Яндекс.Метрика